## Key takeaways
- Choose your replacement around the management problem you need to solve, rather than assuming every existing component needs replacing.
- Ask for separate compatibility evidence for credentials, readers, controllers and data; support for one does not prove compatibility with the others.
- Make internet loss, power failure, credential cancellation and emergency procedures part of a witnessed acceptance test.
- Agree data exports, retention periods, supplier exit terms and a staged rollback plan before signing.
- Compare installation, subscriptions, maintenance, training and eventual exit over the same evaluation period.

You need a Paxton Net2 alternative, but you also need to keep people entering the building while you change systems. The right replacement is one that meets your management needs, has verified compatibility with anything you retain, and passes documented safety and outage tests. A feature list alone cannot establish that.

Start with the reason for changing: remote administration, several buildings, difficult credential management or a wider building-management project. This guide is a procurement framework, not a claim that any replacement connects directly to an existing Net2 installation.

## Choose a Paxton Net2 alternative by operating model

Write down the work you want to improve before choosing the architecture. “Cancel a departing contractor’s access without visiting the site” is a useful requirement. “Modernise access” is not.

Compare locally managed and cloud-managed proposals against the same tasks. Neither label tells you how doors behave during an outage, who maintains the system or how quickly permissions reach each controller.

For a single building with an on-site facilities team, local administration may suit the operating model. For a distributed portfolio, prioritise demonstrations of remote administration and clearly separated staff permissions. These are buying priorities, not guarantees about either approach.
**Compare operating responsibilities**

|  | Locally managed proposal | Cloud-managed proposal |
| Administration | Where can staff make changes? | How are remote permissions controlled? |
| Maintenance | Who maintains servers and backups? | Who maintains controllers and connectivity? |
| Failure behaviour | What happens if the server fails? | What happens if connectivity fails? |
| Supplier exit | Can configuration and records be exported? | What can be exported before cancellation? |

*Use these questions to assess proposals, not as assumed characteristics of every local or cloud system.*
Give bidders the same door list and scenarios. Ask them to identify what their proposal replaces, what it retains and which responsibilities remain with your team. Keep optional parking, [intercom](/features/intercom-access) and alarm work separate so you can judge the access-control proposal on its own merits.

## Check compatibility in four separate layers

“Reuse your existing hardware” needs an itemised answer. A working lock does not establish reader compatibility, and a readable fob does not establish that its existing permissions can transfer.

| Layer | Evidence to request | Acceptance check |
|---|---|---|
| Credentials | Fob or card technology, format and sample readings | Test representative credentials, not just a newly supplied card |
| Readers | Model, interface, wiring and power requirements | Prove operation on the proposed controller |
| Controllers and door equipment | Replacement scope, lock load, power supply, door contacts and exit devices | Test the complete door assembly |
| Software and data | Export sample, field mapping and permission rebuild plan | Reconcile people and access rights before activation |

[IEC 60839-11-5](https://webstore.iec.ch/en/publication/33414) specifies OSDP communication between access-control units and peripheral devices. OSDP support is therefore an interface check, not proof that software, databases or credentials migrate unchanged.

[NIST’s facility-access guidance](https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-116r1.pdf) also highlights existing wiring and reader interfaces as constraints worth assessing. Its main scope is US federal PIV credentials, so use it as technical guidance rather than a universal rule for private buildings.

For TheBuilding.Cloud, [FireBird controllers](/features/firebird-controllers) support Wiegand readers and keypads, including 26-bit cards. That is a specific compatibility statement, not confirmation that every reader or fob at your site can be retained. Require a site survey and pilot-door test.

> **Example:** Picture a 40-flat block in Rotterdam replacing its management system. Its survey should assess the communal entrance, cycle-store door and vehicle gate separately. Success at the entrance does not prove compatibility at the other openings.

## Test the daily work, including exceptions

Ask suppliers to demonstrate your actual administration tasks. Include adding someone, changing their doors, replacing a lost credential and removing access at the end of a tenancy or employment.

Then test the awkward cases: a resident without a smartphone, a cleaner arriving outside office hours and a manager covering another building. Name who provides assistance and how that person verifies an access request.

TheBuilding.Cloud’s [access control](https://thebuilding.cloud/features/access-control) uses entrance groups to organise door permissions. When someone is switched off, removed from a door group or deleted, their PINs, [cards and QR codes](/features/pin-codes-cards-qr) are automatically removed from the readers. Its [passkey access](https://thebuilding.cloud/features/passkey-access) lets users set up a door key on their own phone using face, fingerprint or phone passcode; setup invitations arrive by email, not SMS.

Ask to see both the normal workflow and its exceptions. Can your team identify someone who has not completed setup? What access option will you provide while they need help?

Where maintenance handover matters, [issue reporting](https://thebuilding.cloud/features/issue-reporting) lets residents submit photos, videos, voice notes or files and follow status and replies. Treat this as an operational benefit, not a substitute for checking the door hardware.

## Make failure tests a purchase condition

Do not accept “works offline” without a definition. Ask what happens to existing permissions, new permissions, cancellations and event records when connectivity is lost. Test server availability separately from the building’s internet connection.

Use a written acceptance schedule:

1. **Record the starting state.** List enabled credentials, [door schedules](/features/door-schedules) and expected permissions.
2. **Interrupt connectivity safely.** Witness entry behaviour and attempt an authorised permission change.
3. **Restore the connection.** Check which changes and events appear, and identify any gaps.
4. **Test power-loss procedures.** Have the installer demonstrate the agreed backup and recovery behaviour.
5. **Verify emergency and accessible use.** Obtain sign-off from the responsible local specialists.

Keep expected results, observed results and unresolved faults in the handover record. Agree who can authorise acceptance and which failures prevent further rollout.

Fire release, emergency egress and accessibility requirements depend on the jurisdiction and building. Remote unlocking or a cloud alarm notification is not evidence that the physical door arrangement meets those requirements.

> **Example:** At a hypothetical office building in Chicago, test a revoked contractor credential during a controlled connectivity outage. The purpose is to establish the proposed system’s actual behaviour, not assume that a cancellation reaches an isolated controller.
**Review access-control plans** Compare TheBuilding.Cloud’s published plans and entrance limits for your replacement project. https://thebuilding.cloud/pricing
## Set data and privacy terms before migration

Request a sample export before signing. Check whether it contains people, credential identifiers, entrance groups, schedules and logs, or only a contact list. Ask which settings must be rebuilt manually and how you would leave the new supplier later.

Under the [EU GDPR](https://eur-lex.europa.eu/eli/reg/2016/679/oj/eng/), identifiable access records are personal data. Storage limitation does not create one universal retention period. Processor contracts must address return or deletion at the end of the service, subject to legal retention requirements. Individual data-portability rights do not guarantee that a building’s complete configuration can move between suppliers.

Include old databases, backups and installer-held copies in your disposal plan. Confirm hosting and support locations, administrator access and contractual responsibilities.

If a proposal introduces biometric recognition, commission a separate privacy review. UK ICO guidance addresses lawful basis and special-category conditions and is under review following legislative changes. Illinois BIPA imposes specific duties on covered private entities; it is not a nationwide US rule. Australia’s OAIC warns that rapidly discarding facial-recognition information still counts as collection.

Distinguish phone-based passkey verification from a building collecting biometric templates. Ask what information actually leaves the device and reaches each organisation. Do not treat all products described as “biometric access” as the same arrangement.

## Compare full costs and stage the cutover

Ask every bidder to price the same scope over the same evaluation period. Separate mandatory work from optional improvements.

- Survey, controller replacement, readers, cabling, locks and power supplies.
- Subscriptions, connectivity, credentials and replacement credentials.
- Data preparation, permission rebuilding, training and resident communications.
- Maintenance, fault attendance, battery replacement and software support.
- Final exports, supplier exit assistance and equipment disposal.

For context, TheBuilding.Cloud’s [published plans](https://thebuilding.cloud/pricing) are Free at £0, Pro at £95 and Enterprise at £150 a month, in GBP. Free and Pro have plan limits and optional add-ons; Enterprise usage is metered and billed monthly. These are platform prices, not installed replacement quotations.

Agree the cutover sequence before ordering equipment. A pilot should represent your difficult doors and user needs, not just the easiest entrance.
**A controlled replacement sequence** Survey Record doors, wiring, readers and credentials.; Prepare Clean data and confirm access rights.; Pilot Test normal use, failures and rollback.; Roll out Change agreed doors in controlled stages.; Hand over Reconcile users and close outstanding faults. *Agree an owner and acceptance evidence for each stage before moving to the next.*
Record which system controls each door during transition. Give residents or staff clear instructions, a contact route and any temporary access arrangements. Keep the old configuration available for the agreed rollback window, with controlled access to it.

Do not retire the previous system merely because the new door opens once. Reconcile the approved user list, check cancellations, close outstanding faults and collect the handover documents first.

## Where to start

Prepare a door schedule, an approved user-and-permission list and a page of acceptance tests. Send the same pack to each shortlisted supplier and request an itemised reuse assessment.

Choose the proposal that proves its fit: daily administration, credible failure behaviour, documented migration and a workable exit. That evidence matters more than the longest feature list.

## Frequently asked questions

### What should I look for in a Paxton Net2 alternative?
Start with the problem you need to solve, such as remote administration, managing several buildings or simplifying credential changes. Then assess hardware reuse, permission management, outage behaviour, support and total cost. Require a pilot and written acceptance tests rather than relying on an architecture label or a feature comparison.

### Can I keep my existing fobs, readers, locks and cabling?
Possibly, but assess each component separately. Ask your installer to identify credential technology and format, reader interfaces, cable suitability, lock loads and power requirements. Test representative existing credentials on a complete pilot door. Compatibility with one reader protocol does not establish that controllers, permissions or the existing database can transfer.

### Can TheBuilding.Cloud import people from an existing access-control system?
TheBuilding.Cloud supports people imports from CSV or Excel, with ready-made column layouts for exports from more than 25 access-control and intercom systems, including Paxton. This is a people-import capability, not a promise to transfer every Net2 setting, credential or event record. Validate a sample export and agree the field mapping before migration.

### Will a replacement access-control system work without internet?
Do not assume this from the words cloud-managed or locally managed. Ask the supplier to demonstrate entry, schedules, permission changes, credential cancellation and event recovery during a controlled outage. Record which functions continue, which wait for reconnection and what staff must do. Test power failure separately from internet loss.

### How can I replace access control without disrupting residents?
Use a staged migration with a representative pilot door, checked permissions and clear communications. Agree temporary access, out-of-hours assistance and rollback responsibility before cutover. Track which system controls each entrance during the transition. Retire the previous system only after acceptance tests, user reconciliation and handover are complete.

## Sources
- [IEC 60839-11-5:2020: Open Supervised Device Protocol](https://webstore.iec.ch/en/publication/33414)
- [NIST SP 800-116 Rev. 1: Guidelines for the Use of PIV Credentials in Facility Access](https://nvlpubs.nist.gov/nistpubs/SpecialPublications/NIST.SP.800-116r1.pdf)
- [EU General Data Protection Regulation, Regulation (EU) 2016/679](https://eur-lex.europa.eu/eli/reg/2016/679/oj/eng/)
- [ICO: Biometric data guidance, biometric recognition](https://ico.org.uk/for-organisations/uk-gdpr-guidance-and-resources/lawful-basis/biometric-data-guidance-biometric-recognition/)
- [Illinois Biometric Information Privacy Act, Section 15](https://my.ilga.gov/legislation/ilcs/fulltext?DocName=074000140K15)
- [OAIC: Facial recognition technology, a guide to assessing the privacy risks](https://www.oaic.gov.au/privacy/privacy-guidance-for-organisations-and-government-agencies/organisations/facial-recognition-technology-a-guide-to-assessing-the-privacy-risks)